|
Since Hanford cleanup began, much of the focus has been on resolving immediate threats: concerns about tanks that might catch fire or explode; concerns about spent nuclear
fuel stored in leaking, earthquake-vulnerable basins; and concerns about tons of unstable plutonium. As mentioned, we’ve seen great progress on all of these issues.
After 15 years of cleanup, we have reached a pivotal place in Hanford cleanup. Most of the immediate risks have been successfully resolved. Now the focus is squarely on the quality of the remaining cleanup. And there is considerable debate about that issue.
There are still plenty of long-term risks. Extensive groundwater contamination remains and huge amounts of waste are still moving in Hanford’s sub-surface to the groundwater, including high-level radioactive waste leaked from the tanks. Highly radioactive materials remain in unlined burial grounds. And, until we can put those vitrification facilities to use, 53 million gallons of high-level waste remains in 177 underground storage tanks.
In recent years, DOE Headquarters has stressed a quicker, less expensive cleanup. This is a key part of their accelerated cleanup program and their more recent riskbased end states initiative. Both mean leaving more waste in place. Both will require institutional controls and other restrictions to keep people away so as not to be harmed by the waste left behind.
DOE also proposed changes in the tank waste treatment program consistent with the push by DOE Headquarters to reduce the cost and time of cleanup. The Tri-Party Agreement requires that the tank waste all be vitrified. In the fall of 2001, Office of River Protection Manager Harry Boston said DOE was exploring alternatives to vitrifying all of Hanford’s tank waste in hopes of saving tens of billions of dollars and completing the cleanup decades ahead of schedule. Three technologies were examined and DOE is now resting its hopes on another form of vitrification to treat the majority of Hanford’s tank waste.
If there is one lesson in reviewing the first 15 years of Hanford cleanup – and this one lesson is repeatedly evident – it’s that there is no quick fix for the long-term risks at Hanford. DOE must simply continue with the methodical approach as outlined by Tri-Party Agreement milestones to lessen and ultimately eliminate these hazards.
The lessons from Hanford’s past are among the reasons we believe it is important to document the Hanford cleanup. We can see that the cleanup challenges at Hanford are continually underestimated in terms of their difficulty, their complexity, and their cost.
In addition, by documenting the commitments, the activities, the progress and failures, over the long period of time that cleanup will take, we can help to ensure that the original goals for cleanup are fulfilled. Otherwise, it can be all too easy to lose track of previous commitments and to gradually move in other directions.
In writing this report we have once again drawn heavily from coverage by the news media – the Tri-City Herald in particular, but also from the Oregonian, the Seattle Post-Intelligencer, the Associated Press and other media sources.
As we have now passed the 15th anniversary of the TPA, some of the same concerns and questions we have dealt with before still remain. Funding has and likely will always be a major issue. Those of us concerned about Hanford cleanup have been somewhat nervous about the impact of DOE’s plans to accelerate closure at several sites around the nation, such as Rocky Flats in Colorado and Fernald in Ohio. Getting Congress to appropriate sufficient funding for DOE’s environmental cleanup program has been successful because there has been support from all the states impacted by DOE facilities. We worry about what happens to that support when sites are closed in Colorado, Ohio and other states. Will the Congressional delegations from those states still fight for cleanup funds in other states? This is not a new question. It is one that has been asked for several years. But, it is one we may begin to see the answer to within the next few years.
Federal funding for Hanford cleanup is expected to peak with the fiscal year 2006 budget. However, unlike at Rocky Flats and Fernald, cleanup at Hanford will continue well beyond 2006. Yes, plutonium stabilization is complete, and yes, the spent fuel project will soon be complete, and those were very expensive projects. But, there are other needs at Hanford which require funding. Hanford still has no facilities to treat or package remote-handled transuranic waste. Until those facilities are in place, no work will be done to retrieve waste from burial grounds such as 618-10 and 618-11 – which pose a long-term threat to the Columbia River. The groundwater protection program has been under-funded for years. Lack of funding has also resulted in abandoning plans to move Hanford’s strontium and cesium capsules to dry storage. And of course, construction of the tank waste treatment facilities will require a continued large investment of funds for the next 5-7 years.
The public’s insistence that cleanup continue has – without question – had a huge impact at Hanford. The successes at Hanford are a shared accomplishment by all who have worked to see cleanup move forward. But the job is far from over and your continued involvement is absolutely necessary. As you review Hanford Cleanup:The First 15 Years , rejoice in the accomplishments, shake your head at the missteps, and steel yourself for the hard work yet to be done.

Some Hanford facilities — such as N Reactor above — are located very close to the Columbia River. The zig-zag trench at the bottom of the photo was a liquid waste disposal trench. Another trench is just out of view, farther to the left. The soil and groundwater between the trench and the river is heavily contaminated.

The photo above shows the hazardous environment that many workers face in trying to clean up Hanford.
|